== Microsoft Project ==
== Microsoft Project ==
A time management plan using Microsoft Project (MS Project) must be created. You can learn Microsoft Project by doing the [[MS Project Skill Builder]]. This plan must include all tasks related to the project. The MS Project schedule should include the following:
 
Create a construction schedule using Microsoft Project. Model the schedule after other sample construction projects. The items included in this schedule include:
* Clearing site
* Laying foundation
* Studs and structural members
* Wall construction and window installation
* Painting
* Electrical wiring and lighting installation
* Plumbing
 
You can learn Microsoft Project by doing the [[MS Project Skill Builder]]. This construction schedule must include all tasks related to the project. The MS Project schedule should include the following:
 
* Minimum of 20 tasks.
* Minimum of 20 tasks.
* Milestones should be clearly indicated on the project plan (duration of zero days).
* Milestones should be clearly indicated on the project plan (duration of zero days).

Revision as of 21:20, 6 January 2020

Microsoft Project

Create a construction schedule using Microsoft Project. Model the schedule after other sample construction projects. The items included in this schedule include:

  • Clearing site
  • Laying foundation
  • Studs and structural members
  • Wall construction and window installation
  • Painting
  • Electrical wiring and lighting installation
  • Plumbing

You can learn Microsoft Project by doing the MS Project Skill Builder. This construction schedule must include all tasks related to the project. The MS Project schedule should include the following:

  • Minimum of 20 tasks.
  • Milestones should be clearly indicated on the project plan (duration of zero days).
  • Each task must include the person responsible for completing the task (resource names).
  • Use the Copy Picture function to include the project plan in the presentations. DO NOT take a screenshot.
  • Gantt chart must be displayed alongside the tasks list (fit onto one slide).
  • Gantt chart must clearly show a progress line.
  • Clearly state during the presentation whether the project is on time, behind schedule or ahead of schedule

For help in planning the project, review the page called How to plan the schedule and calculate costs for a project.