Difference between revisions of "How to Show Cost Data in Presentations"
m (Protected "How to Show Cost Data in Presentations" [edit=sysop:move=sysop]) |
|||
(3 intermediate revisions by 2 users not shown) | |||
Line 1: | Line 1: | ||
<h2>Introduction</h2> | <h2>Introduction</h2> | ||
Line 86: | Line 84: | ||
<tr><td align=right colspan="3"><b>Grand Total</b></td><td align=right>$23000.00</td></tr> | <tr><td align=right colspan="3"><b>Grand Total</b></td><td align=right>$23000.00</td></tr> | ||
<caption style="caption-side: bottom;">Figure 1: A typical Cost Table</caption> | |||
</table> | </table> | ||
<p>Figure 2 shows a more complex cost table where several different units of measure | <p>Figure 2 shows a more complex cost table where several different units of measure | ||
Line 113: | Line 113: | ||
<tr><td align=right colspan="4"><b>Grand Total</b></td><td align=right>$23000.00</td></tr> | <tr><td align=right colspan="4"><b>Grand Total</b></td><td align=right>$23000.00</td></tr> | ||
<caption style="caption-side: bottom;">Figure 2: A Cost Table with several units of measure</caption> | |||
</table> | </table> | ||
<p>Note that numbers are always right adjusted and | <p>Note that numbers are always right adjusted and text is always left adjusted. | ||
There may occasionally be exceptions to this rule, but it is a good starting | There may occasionally be exceptions to this rule, but it is a good starting | ||
point. Also, notice how the column headers are made different in some way to | point. Also, notice how the column headers are made different in some way to | ||
indicate that they are not data themselves. This is typically done by making the | indicate that they are not data themselves. This is typically done by making the | ||
column headers bold | column headers bold text.</p> | ||
<p>For the bottom row, if possible do not show the empty cells; just show the | <p>For the bottom row, if possible do not show the empty cells; just show the |
Latest revision as of 19:59, 18 April 2024
Introduction
In industry, managers are responsible for many projects. They are well aware that most projects do not fail for technical performance reasons, but usually fail because of problems with costs or schedule. Because of this, they pay extremely close attention to cost data given in presentations.
In these presentations, managers are looking for two major items. First, they're looking at the data itself to see if it's within the parameters established for the project. Second, and possibly more importantly, they're looking to see if the presenter has firm control over the project cost data, and is well aware of how the project is doing financially. If they are not confident on the second issue, they will not trust the cost data being shown to support the first issue. Therefore, it is critical that you be able to present cost data effectively, and give the impression of confidence.
Managers are usually not interested in the details of cost data, but want to be able to see how overall costs are derived. They're happy when they see the clear "chain of evidence" in a presentation, especially when the numbers are good. If the numbers are not good, i.e. costs are increasing or beyond the point where we can make a profit, managers may still be willing to give a project person a chance to correct the situation if they think the presenter is in overall control of the situation and understands the costs. If they have no confidence in the presenter, even if the numbers they show are good, they'll have no confidence that the numbers are actually correct. Worse, if the numbers are not good, they'll get the feeling that the situation is out of control, something that usually does not lead to significant career growth.
This page will act as an introduction on how to present cost data well, and therefore be able to gain confidence.
Overall Format
First of all, cost data is so important that it should have its own slide. It may be tempting to save time by including cost data as part of the materials list or in another part of the presentation. You should not do this. It makes it difficult for your teacher to understand the data, especially when various quantities of material are used. It is also not done this way in industry. Make sure this data gets the respect it deserves by giving it its own slide.
The overall format of cost presentation is very easy. The format consists of four columns. The first column is the item being reported, sometimes with the "unit of measure" shown as well, usually in parentheses. The unit of measure is how the item is priced. For example, if you're showing the price of a gallon of gasoline, the unit of measure would be a gallon. However, if you're showing the price of a dozen eggs, in most circumstances the unit of measure would be a dozen (the usual way eggs are sold). For many tables, the only unit of measure is "each". However, for some tables several different units of measure are used. For example, some items might be priced by the set, by the dozen, by length (feet or meters), or by area (square feet). When several different units of measure are used, you should add a separate column showing the unit of measure in order to make the table easier to read. If this column is present, it usually has a header of "U/M" (the abbreviation of Unit of Measure) to save space. The next column is the cost for each unit of measure. For example, if gasoline is $2.69 per gallon, the price shown would be $2.69. The next column is the number of units. Finally, the last column is the "extension", which is nothing more than the cost per unit multiplied by the number of units. Each column also has a header showing what the column contains.
Finally, the total cost for the project is shown in the bottom right corner of the table, and is the sum of the extensions. Figure 1 shows a typical table of costs that would be shown for a project. Note that in this case, only one item has a unit of measure other than "each", so we can just show it in parentheses next to the item.
Item | Unit Cost | Quantity | Total |
Fuselage | $10000.00 | 1 | $10000.00 |
Wings | $5000.00 | 1 | $5000.00 |
Tail | $1000.00 | 2 | $2000.00 |
Elevators | $500 | 2 | $1000.00 |
Labor (hours) | $50.00 | 100 | $5000.00 |
Grand Total | $23000.00 |
Figure 2 shows a more complex cost table where several different units of measure are used:
Item | Unit Cost | U/M | Quantity | Total |
Fuselage | $10000.00 | Each | 1 | $10000.00 |
Wings | $5000.00 | Pair | 1 | $5000.00 |
Fabric | $20.00 | Sq.Ft. | 100 | $2000.00 |
Cable | $5.00 | Foot | 200 | $1000.00 |
Labor | $50.00 | Hour | 100 | $5000.00 |
Grand Total | $23000.00 |
Note that numbers are always right adjusted and text is always left adjusted. There may occasionally be exceptions to this rule, but it is a good starting point. Also, notice how the column headers are made different in some way to indicate that they are not data themselves. This is typically done by making the column headers bold text.
For the bottom row, if possible do not show the empty cells; just show the "Grand Total" caption and the overall total for the project.
Additional Issues
This project is very small, and therefore all the data easily fits on a single slide. For larger projects this will not be possible. Although managers may be interested in the detailed data, it is still a good idea to present the overall project costs on a single slide. This means that we might have to summarize individual items into groups to show the overall situation.
In this case, when we look at the detailed sheet, we usually see several items which have large costs associated with them. Even a small change in cost on these items can have a major impact on the overall costs of the project. Then, there are a number of minor items, typically involving large quantities, which do not contribute significantly to the overall cost. Frequently, these items are commodities, and therefore do not have significant price fluctuations. In this case, we can group these kinds of items together. Using RoboLAB parts as an example, the RCX block, motors, and sensors typically have a major impact on the overall project cost. On the other hand, things like bricks do not. Therefore, what we'll do is continue to show the high cost items on a line of their own, but lump the low cost items together.
There are several ways we can lump the low cost items. The first way is to lump them by type. For example, we might have a single line of "Bricks" and the total cost for all the bricks In this case we won't show a unit cost or quantity since the overall total will be the sum of a number of all the different kinds of bricks. Another way to group the items would be by major component of the project. For example, we might have a single item of "Gear Train" which consists of all the gears and axles that are involved, and their overall cost. Usually the type of project will guide you on which format to use In any case, with enough summarizing, you should be able to get the overall project cost onto a single slide. However, you should be ready to present the detailed costs if the management wants to see them.
Another issue is the "unit of measure". In most circumstances, the default unit of measure will be "each", so it's not shown. Any different unit of measure (e.g. "pair" for socks, "dozen" for eggs) etc. would be shown in parentheses behind the item. Some companies like to show the unit of measure separately from the item. In this case the item will be in the first column and the unit of measure will be in the second column. The unit of measure for each line is usually shown, even when it's clear wheat the unit of measure is (i.e. "each").
Summary
This format is typical of the formats used in industry. It gives the audience a good idea of the cost information, and also gives them confidence that you have a good grasp of the cost data. As you gain confidence with this format you may want to improve upon it. This is only the beginning of an important topic.