Difference between revisions of "Template:SLDP: Milestone 3 (Robots)"
From EG1004 Lab Manual
m (→Milestone 3) |
|||
(2 intermediate revisions by the same user not shown) | |||
Line 1: | Line 1: | ||
== Milestone 3 == | == Milestone 3 == | ||
''' | '''<span style="color: red;">See [[Media:Eg_milestones.pptx|How To Give a Milestone Presentation]] for the format of a Milestone presentation.</span>''' | ||
'''Milestone 3 Deliverables''': | '''Milestone 3 Deliverables''': | ||
Line 14: | Line 11: | ||
** CAD drawings: top, front, most detailed side, isometric, gear train | ** CAD drawings: top, front, most detailed side, isometric, gear train | ||
** Mindstorms program | ** Mindstorms program | ||
** | ** Updated cost estimate (previous and current). What changes were made? | ||
** | ** Updated Microsoft Project schedule (previous and current). What changes were made? | ||
** Progress update: current state of the project (time, budget, etc.) | ** Progress update: current state of the project (time, budget, etc.) | ||
<b>Look ahead: What tasks are planned between now and the completion of the project?</b> |
Latest revision as of 01:48, 8 January 2020
Milestone 3
See How To Give a Milestone Presentation for the format of a Milestone presentation.
Milestone 3 Deliverables:
- Presentation:
- Project description
- Design approach
- Design changes since Milestone 2
- Mission statement
- CAD drawings: top, front, most detailed side, isometric, gear train
- Mindstorms program
- Updated cost estimate (previous and current). What changes were made?
- Updated Microsoft Project schedule (previous and current). What changes were made?
- Progress update: current state of the project (time, budget, etc.)
Look ahead: What tasks are planned between now and the completion of the project?