== Milestone 2 ==
== Milestone 2 ==
Using MLCad or Lego Digital Designer, prepare four views of your latest design: front, top, most detailed side, and an isometric drawing. Also, create a drawing of your gear trains. Complete your latest Mindstorms program and your latest MS Project plan reflecting any schedule changes. Finally, calculate a revised cost estimate.
Using MLCad or Lego Digital Designer, prepare four views of the latest design: front, top, most detailed side, and an isometric drawing. Also, create a drawing of the gear trains. Complete the latest Mindstorms program and the latest MS Project plan reflecting any schedule changes. Finally, calculate a revised cost estimate.


'''''Look Ahead''': What tasks do you plan between now and Milestone 3?''
'''''Look Ahead''': What tasks are planned between now and Milestone 3?''


'''Milestone 2 Deliverables''':
'''Milestone 2 Deliverables''':

Revision as of 22:21, 8 September 2014

Milestone 2

Using MLCad or Lego Digital Designer, prepare four views of the latest design: front, top, most detailed side, and an isometric drawing. Also, create a drawing of the gear trains. Complete the latest Mindstorms program and the latest MS Project plan reflecting any schedule changes. Finally, calculate a revised cost estimate.

Look Ahead: What tasks are planned between now and Milestone 3?

Milestone 2 Deliverables:

  • Presentation:
    • Project description
    • Design approach
    • Design changes since Milestone 1
    • Mission statement
    • CAD drawings: top, front, most detailed side, isometric, gear train
    • Mindstorms program
    • Cost estimate (previous and current). What changes were made?
    • MS Project schedule (previous and current). What changes were made?
    • Progress update: current state of the project (time, budget, etc.)