== Microsoft Project ==
== Microsoft Project ==
A time management plan using Microsoft Project (MS Project) must be created. You can learn Microsoft Project by doing the [[MS Project Skill Builder]]. This plan must include all tasks related to the project. The MS Project schedule should include the following:
* Minimum of 20 tasks.
* Milestones should be clearly indicated on the project plan (duration of zero days).
* Each task must include the person responsible for completing the task (resource names).
* Use the ''Copy Picture'' function to include the project plan in the presentations. DO NOT take a screenshot.
* Gantt chart must be displayed alongside the tasks list (fit onto one slide).
* Gantt chart must clearly show a progress line.
* Clearly state during the presentation whether the project is on time, behind schedule or ahead of schedule


For help in planning the project, review the page called [[How to plan the schedule and calculate costs for a project]].
You must create a project schedule to manage your time in Microsoft Project. You can learn Microsoft Project by doing the [[MS Project Skill Builder]]. This schedule must include all tasks related to the project from the start of the project to Submission. Click [https://nyu.service-now.com/sp?id=kb_article&sysparm_article=KB0018302&sys_kb_id=b996a7281b6210906441c8c11a4bcbce&spa=1 here] to access the guide on how to transfer a file. The Microsoft Project schedule should include the following:
 
* Minimum of 20 tasks, excluding Milestones
* Milestones should be clearly indicated on the project plan (duration of zero days)
* Each task must include the person responsible for completing the task (resource names)
* Use the "Copy Picture" function to include the project plan in the presentations. <b>Do not take a screenshot</b>
* Gantt chart must be displayed alongside the tasks list (fit onto one slide)
* Gantt chart must clearly show a progress line
* Clearly state during the presentation whether the project is on-time, behind schedule, or ahead of schedule
 
For help planning the project, review the manual page [[Planning Project Scheduling & Costs]].

Revision as of 01:30, 30 June 2022

Microsoft Project

You must create a project schedule to manage your time in Microsoft Project. You can learn Microsoft Project by doing the MS Project Skill Builder. This schedule must include all tasks related to the project from the start of the project to Submission. Click here to access the guide on how to transfer a file. The Microsoft Project schedule should include the following:

  • Minimum of 20 tasks, excluding Milestones
  • Milestones should be clearly indicated on the project plan (duration of zero days)
  • Each task must include the person responsible for completing the task (resource names)
  • Use the "Copy Picture" function to include the project plan in the presentations. Do not take a screenshot
  • Gantt chart must be displayed alongside the tasks list (fit onto one slide)
  • Gantt chart must clearly show a progress line
  • Clearly state during the presentation whether the project is on-time, behind schedule, or ahead of schedule

For help planning the project, review the manual page Planning Project Scheduling & Costs.