Revision as of 14:51, 4 May 2018
Request for Proposal: Nano Robotics Challenge(NRC)
This project reflects real life scenarios; the robot must be able to handle minor imperfections in the course.
Introduction and Overview
Specifications
Microsoft Project
You must create a project schedule to manage your time in Microsoft Project. You can learn to use Microsoft Project by accessing the Microsoft Project Student Guide. This schedule must include all tasks related to the project from the start of the project to Submission. Click here to access the guide on how to transfer a file. The Microsoft Project schedule should include the following:
- Minimum of 20 tasks, excluding Milestones
- Milestones should be clearly indicated on the project plan (duration of zero days)
- Each task must include the person responsible for completing the task (resource names)
- Use the "Copy Picture" function to include the project plan in the presentations. Do not take a screenshot
- Gantt chart must be displayed alongside the tasks list (fit onto one slide)
- Gantt chart must clearly show a progress line
- Clearly state during the presentation whether the project is on-time, behind schedule, or ahead of schedule
For help planning the project, review the manual page Planning Project Scheduling & Costs.
Milestones, Benchmarks, and Deliverables
As you work on your project, you will be required to present periodic reports on your progress. We call these Milestones. All of the items assigned in each phase of the project are called Benchmark deliverables. These deliverables often consist of a combination of written submissions, presentations, and demonstrations. Benchmark assessments evaluate the progress of your project.
Preliminary Design Investigation
The Preliminary Design Investigation (PDI) is extremely important, as it lays the groundwork for your project. You will be outlining your project idea, inspiration, and goals.
The PDI must include:
- Cover Page
- Project Overview
- Goals & Objectives
- Design & Approach
- Cost Estimate
- Project Schedule
- Relevant Pictures
An example PDI template can be found here. The PDI is due by Benchmark A. Do not forget to include the items listed above. Use this link to access the VEX PDI Rubric.
Milestone 1
Benchmark Assessment A
Milestone 2
Benchmark Assessment B
Milestone 3
Commissioning
Final Presentation
The Final Presentation will be a technical briefing, similar to the Milestones, but also serves as a sales presentation explaining why your company should be selected instead of the competition.
Your Final Presentation must include:
- Company profile
- Company name
- Employee profile, role(s), and qualifications
- Mission statement
- Problem statement
- Why is the project happening?
- What does the audience need to know?
- Project objective
- What is the purpose of your project?
- Who does your project help?
- What problem does your project solve?
- Project description
- Specify LEED certification
- Examples of LEED implementations in Revit
- Revit drawings
- All floor plan drawings
- Dimensions
- 1:240 scale
- Views of exterior of building: front elevation, side elevation, isometric elevation
- Dimensions
- Specify LEED certification
- Market and product viability
- Does your company have competitors?
- What makes your project unique?
- How does your design compare to competitors - cost, quality, features?
- Is the project versatile?
- What is the price of your project?
- Conclusion
- Reiterating project purpose
- Highlight project features
- Future goals of the company
- Why should your company be awarded this contract?
- Video pitch
- Price of project
- Walkthrough animation of building in Revit
- Embedded into Final Presentation
- Problem statement
- Solution overview
- Company description and qualifications
- Source code of program
- Cost estimate
- Microsoft Project schedule
- Video demonstration
- Why should the company be awarded this contract?
Submission
All SLDPs must be submitted online. Please visit this page for the link to the Project Submission form and each SLDP group's individualized login information shown to you on the SLDP submission tab. To submit, you must login to the EG1004 website using this special login information shown to you on the SLDP submission tab. Submitting with your NYU account or any other account will generate an error.
Please note the deliverables for this project are as follows. If any of the following items are missing, you will be penalized. Give yourselves plenty of time to upload all necessary files, especially the large ones which take longer. Be sure to click submit at the bottom of the form. The following list includes deliverable items that are expected from your group:
- Submission deliverables:
- Final presentation
- Final program
- Final MS Project Schedule
- Final cost estimate
- Resume(s) (No fictitious resumes will be accepted.)
Early Submission
If you submit your project one academic week early (before the end of your lab period the week before the Final Submission Deadline), you are eligible for a bonus that will be added to your final semester-long project grade. You must submit all deliverables one academic week before the submission deadline (see syllabus for exact date). The deliverables received early are the ones you will use in your presentation. No adjustments to the submitted deliverables will be accepted.
Late Submission
Late Submission is not allowed. If you do not Commission or Partial Commission by the deadline set forth in the syllabus, you will not be allowed to submit and will receive a zero for the project grade. In order to receive Partial Commissioning, two TAs must evaluate the project and determine its degree of completion according to the Commissioning requirements and you will be given a grade accordingly. Please refer to the EG1004 Grading Policy for more information.